Guys,

Just like to know is there is a tutorial (ebook or video) on how to input resources (labor, non-labor, etc.) in p6? Paul Harris’ book do not give a clear insight on how to really input resources nor the training that i get just recently, i was told that there is another module for resources and what we learned is just the basic 101. I have been a P3/P6 for a while now and is still compuse in inputing resources in the project schedule i worked on.

Thanks in advance and cheers!

Ruel

4 replies

Oldest first
  1. 0
    Joseph Ador ·
    Ruel,

    I cant find a tutorial but hope this would help..

    you can start making resourses in any kind u want @ Resources window. Add a resources name or you can copy existing resources(then edit) and view the bottom details of resources. Then modify the details in Details tab, you can choose labor, non labor, materials. And make sure you will specify the calendar of the resources, corresponding to the activities calendar, it must be the same.

    If you are prompt to monitor the resources with corresponding units and cost, just go to unit and prices and indicate price/unit of the resources you added and the maximum unit/time u will allow for the resources to work on specific activities.
  2. 0
    Rodel Marasigan ·
    Ruel,
    I uploaded the Steps on how to setup a resource in P5 or P6 at Snips. Click the link below
    Resource Setup
  3. 0
    Duy Pham ·
    Thanks Rodel for your value materials.

    Regards.
  4. 0
    Ruel Camaquin ·
    Rodel,

    Thanks for this info, at least it clears-up my confusion on resources.

    Salamat,

    Ruel