Baseline Assigned Slip Away
In the Open Standard
Izam ZakariaMember for 20 years 4 months
- Created
- 1
- 2
0
Gents,
I’ve updated schedule and now I make it as baseline to the new schedule.
But the problem is some of baseline plan date slipped from the original and i realized it was the completed one(100%) for instance it’s completed on Apr but the date now extended to June.
Why this thing happen?
I’ve updated schedule and now I make it as baseline to the new schedule.
But the problem is some of baseline plan date slipped from the original and i realized it was the completed one(100%) for instance it’s completed on Apr but the date now extended to June.
Why this thing happen?
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?