Baseline Assigned Slip Away

Izam ZakariaMember for 20 years 4 months
Created
1
2
0
Gents,

I’ve updated schedule and now I make it as baseline to the new schedule.

But the problem is some of baseline plan date slipped from the original and i realized it was the completed one(100%) for instance it’s completed on Apr but the date now extended to June.

Why this thing happen?

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Izam,
    Baseline use planned date and not actual date. If you wanted to show actual date, link below thread where I explain how to use actual date on baseline.
    How to set baseline after the revised schedule Post #2