Tracking layout used in Thresholds

Haresh JayanthMember for 20 years 1 month
Created
1
3
0
We have a tracking layout which is used in Thresholds , what is the use of the layout in Thresholds.....How it is used when issues are identified......

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Haresh,
    You need to assign a tracking layout to an issue to graphically display the information surrounding the issue, then use the Issue Navigator (choose Tools, Issue Navigator) to open this layout in the Tracking window.