Summary Schedule % Complete

Behnaz SoleimaniMember for 16 years 5 months
Created
4
2
0
hello
a qusetion about Summary calculation for Schedule % Complete in P5?
what is the basis of calculation for summary schedule % Complete ?
thank you
Behnaz

4 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Behnaz,
    By default if not resource cost loaded a proportion of duration up to the data date. If resource loaded with cost a proportion of cost up to the data date.
  2. 0
    Behnaz Soleimani ·
    thank you very much sir;
    but when thsre is not any resource assign to activities, their schedule % Complete in summary calculated zero .
    another question, when we have diffrent resource assign to activities,is it possible that it calculate Schedule % Compltet in summary base on specific one ( not all cudgeted cost, just for example for Labor unit cost)
    thank you
    Behnaz
  3. 0
    Rodel Marasigan ·
    Behnaz,
    All cost will be calculated. If no cost but have resource unit only then it will not included in calculation. (i.e. resource without rate)
  4. 0
    V Kutty ·
    Thanks, its been very useful.