I am trying to get to grips with resourcing and levelling.
an example of my query...
I have two 20 day activities, both pipe laying. I have decided that the same four man gang (which I have defined as a 8hr/day labour resource) can do both jobs, in sequence. The sequence is now 40 days long, as expected.
Then if I need the first job to happen faster, I update the resource to work 16h/d instead of the original eight. This could be determined as either 1. I assign another gang or 2. The gang work twice as long each day. This is all fine and the first activity reduces to 10 days and the second activity starts 10 days earlier, as expected.
Now if I revert back to the original scenario, and decide that it is the second activity that will be reduced in time, employing the same method, it no longer becomes constrained by the resource and the 2 activities now run in parallel. This was not the desired or expected effect. If I now look at the resource useage, this resource is overallocated, even though levelling is switched to automatic.
Does anyone know whats happening? Or how to address it?
Thanks guys,
Dean.
an example of my query...
I have two 20 day activities, both pipe laying. I have decided that the same four man gang (which I have defined as a 8hr/day labour resource) can do both jobs, in sequence. The sequence is now 40 days long, as expected.
Then if I need the first job to happen faster, I update the resource to work 16h/d instead of the original eight. This could be determined as either 1. I assign another gang or 2. The gang work twice as long each day. This is all fine and the first activity reduces to 10 days and the second activity starts 10 days earlier, as expected.
Now if I revert back to the original scenario, and decide that it is the second activity that will be reduced in time, employing the same method, it no longer becomes constrained by the resource and the 2 activities now run in parallel. This was not the desired or expected effect. If I now look at the resource useage, this resource is overallocated, even though levelling is switched to automatic.
Does anyone know whats happening? Or how to address it?
Thanks guys,
Dean.
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?