How to provide page break as per our requirement

Haresh JayanthMember for 20 years 1 month
Created
5
2
0
Dear All,

The page break in page setup , option tab is deactivated.....How to activate the page break. I want to give desired page break as per my requirement.

regards,

Haresh Jayanth

5 replies

Oldest first
  1. 0
    Samer Zawaydeh ·
    Dear Haresh,

    What exactly are you talking about? Seems that you are describing a MS office document.

    With kind regards,

    Samer
  2. 0
    A D ·
    Hi Samer,

    This is abt P6. In the page setup option, there is a check box for Page break. But it is for group setting, I am not sure what P6 means by group, but definitely it is not like excel wherein we can drag the page break line to suit our view.

  3. 0
    Samer Zawaydeh ·
    Dear Ravi,

    Thank you for your note. I will check on this.

    With kind regards,

    Samer
  4. 0
    Rodel Marasigan ·
    "Break Page Every Group" option in P6 page setup is used to print a page by group specify in Group & Sort Function. The first grouping used will dictate this grouping but if indent options is used or tick in Group & Sort function this “Break Page Every Group” option will be disable.
    Ex: If Group & Sort by:
    WBS
    AREA

    WBS will be used for Break Page Every Page. Meaning every change in WBS will be print in another page.
  5. 0
    A D ·
    Thanks Rodel