Skip to content

Base Program Updation

Arun VasanthMember for 17 years
Created
1
4
0
My dear friends
At last I have finalized the program.
Please tell me hw to update in P6 by duration % or physical % ....

I have update only in P3 only

Please help friends

Regards
Arun Vasanth

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Arun,
    It’s almost the same as P3 but P6 response depends on your Duration type settings and Percent Complete Type settings and other project settings.
    On Activity Detail Status tab enter the Percent Complete whether physical or durations % complete.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?