Skip to content

Change of Budgeted Units / times Resources

Haresh JayanthMember for 20 years 1 month
Created
1
3
0
Hi,

i have notice now , that primavera automatically calculates the budgeted units / time as equal to 1 , whenever i assign a resource to an activity....accordingly it calculates the Budgeted units...For eg if an activity is having 6 days duration , budgeted units taken by primavera is 6etc......

My earlier settings, was that , it calculates Budgeted units...whenever i assign a resource is as given below i.e.

Budget units = 8hrs (working hours per day) X duration of the activity.....

I want to return back to my earlier settings , can anyone guide me , how do i return back to my earlier settings???

thanks,

regards,

Haresh Jayanth

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Haresh,
    The settings that controls the default unit/time of resource is under Resource-> Detail tab. Change Default Unit/Time of the resource use to 8.00/d.

    Note: Planning unit setting control the unit/time. Under Users Preferences-> Time Units tab-> Unit Format. If hour is selected then Default unit/time = 8.00/d, if day is selected then 1.00/d

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?