How to define "Recovery Schedule" ?

Irfan KhanMember for 17 years 3 months
Created
4
3
0
Hi to all,

I m working as a contractor & my schedule is behind from my Target. My client need Recovery Schedule so anybody tell me how to prepare Recovery Schedule.

Need urgent reply,


thanks.....

4 replies

Oldest first
  1. 0
    Mike Testro ·
    Hi Irfan

    There have been many discussions on this topic on PP - use the search facility and you will get all the advice you will need.

    Best regards

    Mike Testro
  2. 0
    Irfan Khan ·
    thanks for reply,

    but tell me a basic way to prepare Recovery Schedule.

    thanks
  3. 0
    Mike Testro ·
    Hi Irfan

    Adjust logic
    Increase resources
    change calendar
    change work pattern

    It is all set out in more detail in the forum plus all the other things that you have to take into account - so do your own research please.

    Best regards

    Mike Testro
  4. 0
    Vikas Viswam ·

    Hi Irfan   Herez how I make

    Hi Irfan

     

    Herez how I make it

     

    1. Take a copy of latest updated prog

    2. This prog is delayed prog, plse put your recovery finish date, as a must fish by date, to project finish

    3. Now filter for longest path

    4. Analyse the path and shorten the path by 1. reducing rem dur of in progress 2. reducing Org dur of not started

                                                                  3. Changing the logics 4. changing calendar etc

    5. Do this and filter for next longest path and shorten it

    6. At last you will match with the recovery finish date

    Regards

     

    Vikas Viswam