P6.1 distribution of budget or units over WBS
In the Open Standard
Roozbeh TaheriMember for 23 years 5 months
- Created
- 3
- 3
0
are there any ways to asign budget or units to wbs level and have its distribution over time.
I have budget of each wbs but not activities at the moment, and I want to generate a planned curve based on available information, but it seems in order to have distribution of units or budget over time, they are requred to be assigned to activities rather than wbs
I have budget of each wbs but not activities at the moment, and I want to generate a planned curve based on available information, but it seems in order to have distribution of units or budget over time, they are requred to be assigned to activities rather than wbs
3 replies
Oldest firstLog in or join to reply