P6.1 distribution of budget or units over WBS

Roozbeh TaheriMember for 23 years 5 months
Created
3
3
0
are there any ways to asign budget or units to wbs level and have its distribution over time.

I have budget of each wbs but not activities at the moment, and I want to generate a planned curve based on available information, but it seems in order to have distribution of units or budget over time, they are requred to be assigned to activities rather than wbs

3 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Roozbeh,
    In order to assist your query I need to clarify something. Is the budget assigned in WBS Summary task using resource or budget assigned using budget log in WBS Window?

    If the budget is assigned on WBS Summary task then the answer is Yes but if the budget assigned using budget log in WBS Window then the answer is NO.

    Note:
    Budget log is for information only and normally used for initial planning / budgeting. The proper use if this field are for comparing initial budget to current budget of the Projects.
  2. 0
    Roozbeh Taheri ·
    Rodel,

    I haven’t done any budget asignment yet, and I do not have any wbs summary type activities in the schedule neither.
  3. 0
    Rodel Marasigan ·
    Roozbeh,
    You can create WBS Summary Task activity for every WBS that have budget against it. You don’t need to create link as it was automatically define the durations and start/finish date based on activities underneath within WBS band. Once created you can assign budget cost using resource or expenses. Resource is more flexible than expenses but both can produce budget spread and s-curve.