Is there any problem deleting the data rows in SQL tables refering to deleted data from primavera?

2 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Ali,
    Deleting mark as "deleted" data in Primavera SQL Database will not harm in Database. Just curious why you need to do that as Damon by default is running weekly which main function is deleting all deleted data’s.
  2. 0
    Ali Farhat ·
    I linked some tables from SQL database to access tables, i use these tables to insert data by copying them from excel sheets...deleted data that appear interrupt me so i usually need to get rid of them immediately.
    thanks Rodel for your reply