Level of Effort
In the Open Standard
Oliver MellingMember for 19 years 5 months
- Created
- 1
- 1
0
Does anyone know how its possible to have a current programme that is on target to meet all baseline dates, but also has level of effort tasks across the project that have less than 1.0 for their SPI?
(This being calculated automatically from duration % complete, all calendars the same)
I have noticed that the at complete duration is greater than the original even though the baseline and current start/finish dates are the same.
(This being calculated automatically from duration % complete, all calendars the same)
I have noticed that the at complete duration is greater than the original even though the baseline and current start/finish dates are the same.