Level of Effort

Oliver MellingMember for 19 years 5 months
Created
1
1
0
Does anyone know how its possible to have a current programme that is on target to meet all baseline dates, but also has level of effort tasks across the project that have less than 1.0 for their SPI?
(This being calculated automatically from duration % complete, all calendars the same)

I have noticed that the at complete duration is greater than the original even though the baseline and current start/finish dates are the same.

1 reply

Oldest first
  1. 0
    Mike Testro ·
    Hi Oliver

    It seems as though you are using up float.

    Best regards

    Mike Testro