Activity Duration at WBS Level.
In the Open Standard
Anujkumar MishraMember for 18 years 1 month
- Created
- 1
- 4
0
I have made a Project Schedule in Primavera V-5,
Based upon the requirement of the project, I have assignd diffrenet caleders to different activities.
Same schedule has been submitted to client.
After importing this schedule in Primavera, discrepency in activity duration has been identified at WBS level of the schedule.
In my system at activity level calneders are assignde while at WBS level there is no calneder. But at clients system there is calnders at activity level as well as WBS level due to this there is difference in activity duration at WBS level of same project schedule opened at clients system and my system.
Kindly help.
Based upon the requirement of the project, I have assignd diffrenet caleders to different activities.
Same schedule has been submitted to client.
After importing this schedule in Primavera, discrepency in activity duration has been identified at WBS level of the schedule.
In my system at activity level calneders are assignde while at WBS level there is no calneder. But at clients system there is calnders at activity level as well as WBS level due to this there is difference in activity duration at WBS level of same project schedule opened at clients system and my system.
Kindly help.
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?