FS RELATIONSHIP Confusing

Kumar SMember for 16 years 8 months
Created
1
2
0
Dear guys, i was refering to the last years project. in the primary baseline bar plan.but there are some relationships which i cannot understand. for ex i have A and B activities which has FS relationship between them. there is no lag. the A activity has FS to some other activity also C . BUT IN THE SCHEDULE THE B activity is starting before the A activity has finished. why is this happening. please clear my doubt..... thanx...

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Kumar,
    It either have mandatory constraints or Act is finished but data date is lower than Act start and finish date.