Schedule % Complete in P6

Duy PhamMember for 17 years 4 months
Created
5
3
0
Hi Rodel,

I have a question: Schedule % complete in P6 is calculated based on what???(duration, unit,...)

Thanks in advance.

Duy

5 replies

Oldest first
  1. 0
    D Artagnan ·
    it’s based on duration.
  2. 0
    Rodel Marasigan ·
    Duy Pham,

    By Default P6 calculate Schedule % Complete by proportion of duration if no resources assigned. If resource is assign without rate or cost P6 will still use duration. If Cost loaded, proportion of cost towards duration if no resource curve assigned. If resource curves is assigned then P6 use curved proportion.
  3. 0
    Duy Pham ·
    Thanks Rodel, D for your clear reply.

    Regards
  4. 0
    Michael Lepage ·

    There's a great article on

    There's a great article on this over at https://www.planacademy.com/primavera-p6-schedule-percent-complete-guide-1/. Hope it helps.

     

    M

  5. 0
    Zoltan Palffy ·

    SCHEDULE % COMPLETE indicates

    SCHEDULE % COMPLETE indicates how much of the activity duration should currently be completed relative to the baseline schedule. This is based on where the data date falls between the activities baseline start and finish dates. 

Log in or join to reply