Global Change Implementation on "Finish Date Column"

Izam ZakariaMember for 20 years 4 months
Created
1
3
0
Guys,

I’m just wonder if we can do global change on "finish date column"

What I did, I imported the excel data onto user_end_date(my forecast date) I want to use global change something like this:

If user_end_date bigger than XXX
Then Finish date = user_end_date

but the problem is I didn’t find "finish date" column instead planned finish date.

so is it we can’t change the finish date automatically?

thx

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Izam,
    Finish date field is a result of current early dates which is not updatable. If you need to update finish date using Global change uses Remaining Early Finish date which is equal to Finish date.

Log in or join to reply