Baseline in P6

Jatinder KUMARMember for 16 years 7 months
Created
1
2
0
Hi

I was going to update my schedule today.First I saved copy of my previous schedule in same node where my current project is.

Then Project..Maintain Baselines..Added saved project as baseline.
Then Project..Assign Baseline..as I put it as primary baseline.
Then I compare my current Finish with primary baseline finish(BL1 Finish) in primavera.Now I am facing two problem:
1)Variance shown in column"Variance BL1" in NOT right.It is taking data from somewhere else & is comparing with current finish date.Is there any default baseline settings too or why it is doing so??
2) Variance BL1 Finish=Current Finish-BL1 Finish It should be -vein case of slippage.But it is showing positive value why?.Example 12June 10 - 20June10=-ve Value.But it is showing postive over there.Why??

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Jantinder,
    When you attached a baseline it will used Baseline Planned date and not Baseline Current Date (Start/Finish) so the formula is BL1 Planned Date - Current Date = Variance. Better check BL1 Planned Date and for more information click below:
    How to set Baseline- After revised the Schedule and to Post #2