Updating Schedule From Schedule A to Schedule B

Izam ZakariaMember for 20 years 4 months
Created
8
3
0
Guys,

Currently I’ve schedule A which is up to Level 3 and schedule B from main contractor which is more detail (level 4).

What is the best practice to update Schedule A (level 3) from main cont schedule update.

Is it we’ve to use level of efforts? If we’ve same WBS, can we direct import from main cont schedule.

Guys your comments on this matter is highly appreciated.

Thank you

8 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Izam,
    If you have the same activity ID of Level 3 Schedule B and schedule A then you can update using direct import otherwise manual update if not.

    The best is to have the level 4 schedule in Schedule A and just run a report on level 3.
    Another way is create a WBS summary activity on Level 3 of Schedule B with the same activity ID of level 3 on Schedule A and export only WBS summary activity to import back to Schedule A using excel export/import functions.
  2. 0
    Izam Zakaria ·
    Rodel,

    It is make sense but I do believe I will have a problem to define critical activities.Never mind I will give a shot first.Any results will advertised here

    Another issue is I’ve one project file which previously was under Project activity codes but now turns to Global activity codes.How do I want to make it everything back as normal? Because my group and sort setting didn’t recognize the activity codes.

    Rodel, I would like to express you a thousand thanks for your helping hand and proposal
  3. 0
    Rodel Marasigan ·
    Izam,
    I fully recommend changing all activity codes to Global and redoing your layout. You don’t need to input again your activity code values in the Project as it will recognize by Primavera. That will works on every projects compare to Project level activity code.
    Another issue is once Activity Code is change to Global it cannot be back to Project unless you change it back using API or direct to the Primavera Database.
  4. 0
    Izam Zakaria ·
    Rodel,

    Back to my first query,I guess you are right, the best way is to have level 4 for Schedule A then we can direct import from schedule B(which is level 4 too)

    If I do the summary on Schedule B level 3 then further transfer to Schedule A level 3 it won’t give the exact links and difficult to analyze the total float plus I can’t press "scheduling button" F9

    But If I do that manually then it will take time because I’ve 3000 activities.

    Oh gosh I’m in trouble I guess.What should I do?
  5. 0
    Rashid Iqbal ·
    Izam,

    We have the same case in many of our projects; we being the contractor maintian a level 4 schedule whereas the CMT group maintains a level 3. What we suggest is to map our activities to their’s. Ussally it is simple for example if we have 15 piping activties they will have 3...so they have to map our 15 to their 3.

    Try for a few activities...make a simple spreadsheet and I hope it will work..Thanks.

  6. 0
    Izam Zakaria ·
    You meants I’ve to do in excel spreadsheet then further implement onto schedule?
  7. 0
    Rashid Iqbal ·
    I can send you a spreadsheet that can give you some idea. If your schedule is simple and you donot have to match the earned hrs then you may not need the spreadsheet.

    My email is

    iqbalr2001@yahoo.com

    drop me a line and I can send the spreadsheet ur way. Thanks.

    R
  8. 0
    Mohamed Hegab ·

    You may need to check the

    You may need to check the schedule integrity after doing such process.  You may perform any unintentional change in the GS's schedule.  You may run it through our Schedule Cracker software to identify any changes and anomilies resulted from the change.

    Good Luck

    Mohamed Hegab,PhD,PE,PMP,MRICS

    Schedule Cracker Team

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?