How to consider miscellaneous costs, and resources

Shareef Abdul AzeezMember for 21 years
Created
5
2
0
Hello

I would like to know how to incorporate miscellaneous costs, labour, plant & materials for activities.

Normally when resources are entered only the major resources come to mind but when actually executed based on the site conditions the resources required may increase and some times additional materials which were not though of such as extra binding wire for steel fixing, plastic sheets for blinding, solitex boards for joints,....

There would actually be a whole list of minor materials and sometimes transportation charges from store to site or within site; then may be cost of water tank for watering, cost of water.

P6 is well built for costing.
Now how do we handle this???

Previously I have worked on costing of a project and the costing was done using an ERP package called BAAN.Here we used to have an item called sundries or micellaneous.
Is it something like this?


Regards
Shareef A Azeez


5 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Shareef,
    You can use LOE activities and assigned expenses, misc materials, sundries...etc...where applicable if you don’t have designated activities for those item. You can also use WBS summary activities (i.e. Construction) for those items and you can specifically change planned date for each resource.
  2. 0
    Shareef Abdul Azeez ·
    Thanx once again Rodel,

    You are the P6 user manual for a lot of planners...

    Now I would like you to detail your reply

    LOE activities are Level of Effort I guess. Is it similar to hammock activity?

    "You can also use WBS summary activities (i.e. Construction) for those items and you can specifically change planned date for each resource".

    can you clarify the above a little more in detail?

    ( WBS summary activities???.... change planned date for each resource???)

    Hope youll have the patience!!!

    Thank you once again Rodel
  3. 0
    Rodel Marasigan ·
    Shareef,
    If the resource is under WBS summary activities or Level of effort activities, you can change the planned date of each resource so the distribution of cost will be based on the estimated planned date. If the activities are sitting at one WBS then use WBS summary activities otherwise use LOE (same as hammock) and link the first activity SS and last Activity FF and assign resource. See sample below:
    Resource Allocation
  4. 0
    Shareef Abdul Azeez ·
    Thanx Rodel

    Now I understand!!!



  5. 0
    Duy Pham ·
    Thanks Rodel so much, this subject was my headache for a long time, but now, no more.

    Thanks Shareef for rising this subject.

    Duy