sure track

Kumar SMember for 16 years 8 months
Created
1
0
Dear Guys,

can we import the sure track project in to primavera p6.

thank you




1 reply

Oldest first
  1. 0
    David Kelly ·
    Yes, but you need to save the project in "Project Groups" or "Concentric" format, then treat as a P3 import....