Critical Path
In the Open Standard
MA
Moutaz AldeibMember for 22 years 9 months
- Created
- 15
- 7
0
15 replies
Oldest first- 0RMRodel Marasigan ·Moutaz,
Possible reasons are:
-> The schedule had a Must Finish by date define which is higher than project completion which give a project float not equal to zero.
-> Project might have define constrain at the last activity or milestone which cause having total float not equal to zero for the rest of activity.
-> Schedule options critical path calculation parameter is negative float. - 0RMRodel Marasigan ·Moutaz,
If the schedule is imported from other software, Primavera default for Milestones is Start Milestone. So if the activity link is FF then Start Milestone is incorrect. Filter all milestones or check the schedule log what milestone activity ID and change it to Finish Milestone. - 0RMRodel Marasigan ·Moutaz,
No! I said if the schedule is import from other software like MSP, Primavera convert it to Start Milestone.
I’m not sure if your schedule source is from other software or not. Who ever gave it to you he/she may import it from MSP. To correct the invalid relationship, it’s either correct the relationship type or the activity type.
Example:
If logic is FF but activity is Start Milestone then it is invalid relationship. So either change relationship type as SS for Start Milestone or change activity type to Finish Milestone.
Vladimir,
Based on MSP to P6 Mapping by default MSP milestone which having start and finish date are converted to Start Milestone. Primavera has only one date in Milestones. It’s either Start Date for Start Milestone or Finish Date for Finish Milestone and cannot have both. I hope that make sense.
Best Regards,
Rodel - 0MAMoutaz Aldeib ·Rodel,
I have got your point, but the problem I have that the project is surely imported from P6 and there is not ilogic link, I do not know what the program means by invalid relationship.
However, if the start milestone linked to another start milestone by relationship FS, does it mean invalid relationship?
Regards,
Moutaz - 0RMRodel Marasigan ·Vladimir,
I did explain it if you read my post #7. "P6 to MSP mapping stated that MSP Activity mark as Milestone will be converted as Start Milestone."
Start Milestone having only Start Date.
Finish Milestone having only Finish Date.
To extend my explanation, Primavera separates Start Milestone and Finish Milestone with their behavior when link to activity.
Ex:
Act1 - FS - Start Milestone = If Act1 finished at 5:00PM (last working hour) Start Milestone start on the following working hour.
Act1 - FS - Finish Milestone = Finish Milestone start or finished at the end of Act1 i.e. 5:00PM
Start Milestone - FS - Act1 = Act1 start together with start milestone.
Finish Milestone - FS - Act1 = Act1 start next working hour or following day if Finish Milestone start/finished 5:00PM.
Best Regards,
Rodel - 0RMRodel Marasigan ·Moutaz,
Like what I have said P6 will accept the link and make no difference but will produce invalid milestone relationship on log report. If you change all FS relationship to SS of all Start Milestone stated on log report and run the schedule again, you see on log report that no more milestones having invalid relationship. - 0RMRodel Marasigan ·Hi Vladimir,
No it does not mean like that. If Activity finished at 8:15AM then start Milestone will start at 8:15 because working hours is not yet finish but if act finish at 5:00PM (last working hour or time) Start Milestone will start following working hour (time) or next day (ex: 8:00AM).
Best Regards,
Rodel
Log in or join to reply