Re-Baseline Schedule
In the Open Standard
Rifky SoedirdjaMember for 16 years 5 months
- Created
- 5
- 3
0
I am currently in progress to Re-Baseline the schedule using data date 25Jun-10 as a cut off date. The schedule is already Units and Cost loaded respectively. I used Price/unit = $1/h, so Units is equal to Cost for this case.
So, as of 25-Jun, status of schedule is as follow :
Total Budgets Units & Cost = 447,076
Actual Units & Cost = 140,105
Units % Complete = 31.34%
But why schedule % complete is still showing 33.57%. How to make this schedule % complete is equal to Units/Cost % complete? I believe when we want to Re-Baseline schedule, all the Plan figures should be reset to the current status (Variance between Current % - Plan% = 0.00%). In this case Current progress is 31.34%.
Please correct me if I am wrong. Thanks.
Rgds,
Rifky
So, as of 25-Jun, status of schedule is as follow :
Total Budgets Units & Cost = 447,076
Actual Units & Cost = 140,105
Units % Complete = 31.34%
But why schedule % complete is still showing 33.57%. How to make this schedule % complete is equal to Units/Cost % complete? I believe when we want to Re-Baseline schedule, all the Plan figures should be reset to the current status (Variance between Current % - Plan% = 0.00%). In this case Current progress is 31.34%.
Please correct me if I am wrong. Thanks.
Rgds,
Rifky
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?