Budget Unit Calculation

Luis GonzalesMember for 18 years
Created
2
4
0
hi to all master

I’m newly in scheduling/planning work and I used P6,I just want to know how to calculate "budget unit" for non labor and labor unit,I have programmed now created by 1 of the planner from our head office and sent it to me to study and update.some of the activities in the programmed has already a budget unit..e.g..activity name=Pile Cap A-zone,duration=32 days,non labor budgeted unit=1400995 and labor 2976262..I am trying to find out how they/he calculated that data,but I can’t find out how?...your help will highly appreciated..

thanks and regards


Luis

2 replies

Oldest first
  1. 0
    Andrew Dick ·
    Luis,
    I would suggest that the figures entered may be a dollar value associated with the activities.
    These numbers may (should) have come from the project estimate.

    You generally wouldn’t let the planning tool create a value on a discrete effort/labor activity, as this information is usually entered manually.

    I would ask the planner that created the schedule how they arrived at that figure and if the answer is an estimate then request a copy of it as you may wish to refer to it at a later date.

    Andy
  2. 0
    Luis Gonzales ·
    Sir Andrew Dick

    Thank you for your advice sir,may be its better to ask the person who created the programme on how he calculated the budget unit per activity.

    thanks and regards

    Luis