How to change OD view

Irfan KhanMember for 17 years 3 months
Created
5
2
0
Hi to all.....

I want to change something in Original Duration Column like that :

Default >> Original Durarion
10

Change into >> Original Durarion
10d

I just want to inset d that will dedicate Days.

Pls somebody help.........

thanks..............

5 replies

Oldest first
  1. 0
    Anbin Ponnith ·
    Hai Irfan
    Try the Following option
    Edit->UserPreference->Dates->Duration Format->(Click) Show Duration Label
    Regards
    Anbin
  2. 0
    Rodel Marasigan ·
    Irfan,
    For label on duration (i.e. 10d)
    Edit-> Users Preferences-> Time Units tab-> under Duration Format tick Show Duration Label.

    For Default duration (i.e. 10)
    Admin-> Admin Preferences-> General tab-> under Activity Duration-> Default Duration change to 10.
  3. 0
    Irfan Khan ·
    Thanks for reply,,,

    but i need this in Small Letter i.e. (10d) but whenever i m going to change in Small Letter is saying that "10d is not valid work/time unit.

    so how to convert it in small letters.....?


    thanks
  4. 0
    Rodel Marasigan ·
    Irfan,
    Admin-> Admin Preferences-> Time Period tab-> under Time Period Abbreviations change the capital to small letter.
  5. 0
    Irfan Khan ·
    thank u Rodel ..........


    regards....