Total float of the first activity

Moutaz AldeibMember for 22 years 9 months
Created
12
1
0
Dear Planners,

the first activity in the time schedule has TF=2 days and the critical activities are only 3 out of 600 eventhough no open end and no constraints.

Regards,

Moutaz

12 replies

Oldest first
  1. 0
    Vladimir Liberzon ·
    Did you level resources?
  2. 0
    Mike Testro ·
    Hi Moutaz

    Following Vladimir’s question here are a few more.

    1. Do you use very long tasks - 30 days plus?
    2. Are you using SS FF Links?
    3. Are you using + - Lead Lags?
    4. Are any tasks set ALAP?

    Best regards

    Mike Testro
  3. 0
    Vladimir Liberzon ·
    Hi Moutaz,

    Do you use multiple calendars in your schedule?

    If you did not use any constraints of Start No Earlier Than type then it may be caused by multiple calendars (and this may be true) or resource leveling (and this is wrong - Primavera does not calculate resource constrained floats properly).
  4. 0
    Moutaz Aldeib ·
    No multiple calendars, no resource in the schedule and no constraints.

    Regards,

    Moutaz
  5. 0
    Rodel Marasigan ·
    Moutaz,
    Check the logic and filter the longest path. I suspect that it was lying on 3 long activities.
  6. 0
    Jeoffrey Reyes ·
    Hi Moutaz,

    Though you have completed your program, you have to check your critical activities then once more link it to be more realistic with your logic.


    cheers,
    JEFF
  7. 0
    Moutaz Aldeib ·
    Thanks everybody for response,

    Rodel, only one activity out of three is long

    I am really stuck with this program, I could not find where is the problem?

    Regards,

    Moutaz
  8. 0
    Mike Testro ·
    Hi Moutaz

    Have another look at thread nr 3

    Best regards

    Mike Testro
  9. 0
    Rodel Marasigan ·
    Moutaz,
    It seems that you have a Must Finish by date define which might be the cause of the problem.
  10. 0
    Shazia khan ·
    Please check,

    press f9 Schedule--Option--Define Critical as ---tick the total float less then or equal to 0h

    may be this can be work for you.
  11. 0
    Moutaz Aldeib ·
    Dear all,

    There is no must finish by constraint and no constraints at all.

    Regards,

    Moutaz
  12. 0
    Jeoffrey Reyes ·
    Hi Moutaz,

    I saw already your schedule. It seems that you have too much float which is not advisable. But to answer your query why you have a Float of 2days in your START WORKING activity?, you have to adjust your lag to its Successor;

    A5310 Hand Over FS 105

    then your float will be Zero. Also, put FF relationship if you are linking to Milestones not FS. As what I have mentioned in my previous post, you have to link a more logical relationship to achieve a good critical path. Try to avoid to much Float its no longer realistic....200days and more...you know what i mean.


    cheers,


    JEFF