Guys,

If in P3, we can import/export the links thru excel, can we do that in P6?I never give a try yet but if not mistaken we can do exactly same like P3. Am i right?

Regards
I-zam

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Izam,
    Yes you can use export/import spreadsheet function in P6 to update progress. Task is for updating activities and Resource assignment is for updating resource loading and actual. You must update one at a time and not both otherwise it will produce an unexpected result.