globsl change issue
In the Open Standard
Kumar SMember for 16 years 8 months
- Created
- 1
- 2
0
dear Guys,
when we apply the global change for the resources then will the change be effected to the present project which is opened or to all the other projects where this resource is assigned.
and i have assigned a UDF for the activities where the resorce changes has to be done. but in the global change tab i am not able to filter that UDF in the resourccce assignment section of global change.
is it neccesary to assign the activty codes to filter the activites ;
why is that the UDF cannot be filtered.
thank you
thank you...
when we apply the global change for the resources then will the change be effected to the present project which is opened or to all the other projects where this resource is assigned.
and i have assigned a UDF for the activities where the resorce changes has to be done. but in the global change tab i am not able to filter that UDF in the resourccce assignment section of global change.
is it neccesary to assign the activty codes to filter the activites ;
why is that the UDF cannot be filtered.
thank you
thank you...
1 reply
Oldest firstLog in or join to reply