SDK
- Created
- 49
- 2
49 replies
Oldest first- 0RSRola Sabbah ·hi every body
when i use the sdk for importing activities it duplicates these activites, one with the id that i inserted anothr with defualt activity stating A10203
when i import relationship it gives error that there is dublicate relationship although there is no duplicates?
what is wrong can any body help?
- 0JRJeoffrey Reyes ·Sometimes, unknowingly, you were setting the activity twice. Try This....Close your P6 first before importing so that the loading will be more faster. Then Open your P6 to check if your imports loaded up. Then for the next procedure of importing, Close again your P6 then import again another set of activities. For relationship, maybe because you have already a duplicate of activities then correspondingly your relationships were affected.
Delete those activities you have imported then try to import again. Let me know.
- 0MSMohamed Saleh ·
Hi everybody can anyone send
Hi everybody
can anyone send me the SDK file in excel format..i cannot find it in my CD.
my email is mo.saleh81@gmail.com
- 0JRJeoffrey Reyes ·
Hi Rola & Mike, I don't know
Hi Rola & Mike,
I don't know why my thread was locked up though many of our PP members can benefit from some suggestions and queries on the Steps using SDK.
Sorry Rola from using your thread. And sorry guys also because I cannot attend to your queries. Currently, I am still attending to very important matters pertaining to my departure in my next destination. So many problems i have encountered till now and i am using only my mobile in responding to all of you.
What is the ground to lock up anyone's thread?
cheers,
JEFF
- 0MEMehmet Egilmezer ·
hi!i only have activity and
hi!
i only have activity and dictionary, can any body send me the wbs.xls, please send it to
mehmetegilmezer@hotmail.com
thanks - 0AKAhmet K. ·
Dear Jeff,Could you pls
Dear Jeff,
Could you pls forward the following excel files and STEP BY STEP GUIDE USING SDK IN SCHEDULE PREPARATION to my email: kochanahm@yahoo.com
1. WBS.xls
2. Activity.xls
3. Dictionary.xls4. Step by step guide using SDK in schedule preparation
Thank you in advance
Ahmet - 0AKAhmet K. ·
Dear Jeff,Could you pls
Dear Jeff,
Could you pls forward the following excel files and STEP BY STEP GUIDE USING SDK IN SCHEDULE PREPARATION to my email: kochanahm@yahoo.com
1. WBS.xls
2. Activity.xls
3. Dictionary.xls4. Step by step guide using SDK in schedule preparation
Thank you in advance
Ahmet - 0SSSundar Singh ·
Jeff, Can you please forward
Jeff,
Can you please forward the step by step guide for SDK to the following Mail id.
Thanks in advance Jeff.
Sundar.
- 0
- 0GGGuo Guo ·
Hello Jeff, Can you please
Hello Jeff,
Can you please forward the step by step guide for SDK to the following Mail, Thanks so much!
guo
- 0AAAlhasan Abdalla ·
here is a link to the latest
here is a link to the latest sdk
- 0RYRiyadh Yahia ·
Hi jeff, can u send me
Hi jeff,
can u send me STEP-BY-STEP GUIDE USING SDK IN SCHEDULE PREPARATION
my email id: riyadh63@gmail.com
best regards
- 0JSJun Sarvida ·
Hi to all, Im new in this
Hi to all,
Im new in this site and Im very enterstied in linking primavera to excel and other format presentation, can any one help me to have a primavera dictionary.xls and wbs.xls pls? Kindly pls email me at junsarvida@yahoo.com...Thank you so much.
JUn
- 0LTLarry Tamayo ·
Jeff,Im new in this site and
Jeff,
Im new in this site and at the same time a new planner, i read your comments/post with regards to the application of SDK in Primavera. Can you send me your STEP-BY-STEP GUIDE USING SDK IN SCHEDULE PREPARATION.
my email add: spenhil@yahoo.com
thank you so much in advance..
Larry
- 0APAmeen Pasha ·
A STEP-BY-STEP GUIDE USING
A STEP-BY-STEP GUIDE USING SOFTWARE DEVELOPMENT KIT (SDK)
FOR PRIMAVERA VERSION 6.x
SCHEDULE PREPARATION
BY: JEOFFREY B. REYES
Sr.Planning Engineer
BUILDING WORKS /
ROAD & INFRASTRUCTURE
Jubail Industrial City, K.S.A.
04 August 10
This short paper is a simple and easy guide in preparing a program or schedule using
Software Development Kit (SDK). This tutorial assumes that you know the basics of
Primavera 6.x. With this tutorial, even you’re a novice you can prepare the program very
easy. Also, another premise is you have already SDK program installed in your PC.
You can find in this exercise a very simple small project just to give you an overview on how
you can deal with the importing of all data you have in spreadsheet to Primavera 6.x. I
provided a sample of Bill of Quantity (BOQ) and Manpower Tabulation for your resources’
reference.
At the end of this exercise, you will come up with the schedule shown below. Just follow the
step-by-step instructions and you can achieve the same. Goodluck!
To start with, first you have to create a New Project and make its Project ID named “C2” and
Project Name as “SDK Guide for C2 House Model” or any Project Name you like. See
illustration below.
Before you start, take a glance first on the sample Bill of Quantity and Manpower Tabulation
that you will be using as your reference in this exercise.
Step 1. In this exercise you will create Two (2) Work Breakdown Structure (WBS) Names
only, Substructure and Superstructure. But this exercise focused only in Substructure. Open
your Excel file for WBS Macro then click WBS tab to set your WBS Name. Proceed to Step 2.
Step 2. After filling up the WBS Names, WBS Codes and Parent WBS ID’s, Go to Login tab
then Put your USER NAME and PASSWORD. Update Project List and select C2 Project ID then
Set WBS. Open your Primavera P6.x program and check your WBS. If it’s ok, then proceed to
the next step.
Note:
If your Primavera 6.x software is open at the same time with your Excel File Macro, you must
close the Primavera 6.x software first and re-open it to load up what you have done in your
Excel File. Do this to the rest of this exercise everytime you will Set your tasks.
Step 3. Setting up your Activities. Open your Activity 6.x Excel File. Put your USER NAME and
PASSWORD then Update Project List. Select C2 Project. Click Activity Details tab to setup
your Activities. Proceed to the next Step.
Step 4. Setting up your activity details to SUBSTRUCTURE WBS. In doing this, see WBS
column, C2.SUB means C2 is the Parent WBS ID and SUB means your WBS Code and put a
Dot separator. For this sample project, Pick STANDARD for your Calendar and make your
activities all Task Dependent. Activity ID is self explanatory in its nature and the Duration is
just an assumption. After finishing the tasks, Go to Login Tab then Set Activity Details. Again,
Open your Primavera 6.x and check if all activities were there. If OK, then proceed to next
step.
Step 5. Set your Relationships. Click Activity Relationship Tab then type all you see in the
screenshots provided below. For Relationship Type, I used Finish-To-Start only. You can try
also other Relationships and put some lags if you like. After finishing the tasks, Go to Login
Tab then Set Activity Relationship. Again, Open your Primavera 6.x and check if all activities
were there. If OK, then proceed to next step.
Step 6. Setting up your Material Resources. Before you proceed, create a Resource ID C2
first and Resource Name C2 RESOURCES FOR SDK GUIDE (or any Resource Name you like) .
Then, Open your Dictionary 6.x Excel File for Resources Details. Put your USER NAME and
PASSWORD then Update Project List. Select C2 Project. Click Resources tab to setup all your
Resources. Proceed to Step 2.
Step 7. Set your Material Resource Dictionary. Click Resources Tab then copy the listed
sample below. In this exercise, I separated the setting up for Material and Manpower to give
way first to Material Resources Rates and Assignments. After finishing the tasks, Go to Login
Tab then Set Resources. Once again, Open your Primavera 6.x and check if all Resources
were there. You will notice that your reources category is in Labor. Change it to material by
clicking the labor then CTLRL+E to copy Fill Down. If OK, then proceed to next step.
Step 8 . Set your Material Resource Rates. Click on Resource Rates Tab, copy the Resource
ID’s and Description in the sample BOQ provided on the outset of this exercise. Effective
Date and Max Units/Time are just an assumption. You can change as you wish. But to have
the same outcome for this exercise just follow the same. After finishing the tasks, Go to
Login Tab then Set Resource Rates. Once again, Open your Primavera 6.x and check if all
Resource Rates were there. If OK, then proceed to next step.
Step 9. In setting up your Material Resource Assignments, Open your Activity 6.x Excel File.
Put your USER NAME and PASSWORD then Update Project List. Select C2 Project. Click
Resource Assignment Tab to setup your Activities. Proceed to the next Step.
Note:
Resource Assignments for Material and Manpower is located in this Excel File.
Step 10. Set your Material Resource Assignment by clicking the Resource Assignment Tab.
Budgeted Units and Remaining Budgeted Units is just the same for a baseline schedule. See
Budgeted Units on our sample BOQ aforementioned in the beginning of this paper. After
finishing the tasks, Go to Login Tab then Set Resource Assignments. Once again, Open your
Primavera 6.x and check if all Resources were correctly assigned. If OK, then proceed to next
step.
Step 11. Setting up your Manpower Resources. Open your Dictionary 6.x Excel File for
Resources Details. Put your USER NAME and PASSWORD then Update Project List. Select C2
Project. Click Resources tab to setup all your Resources. Same thru with Material, the
procedure is just the same. Proceed to Step 2.
Step 12. Set your Manpower Resource Dictionary. Click Resources Tab then copy the listed
sample below. After finishing the tasks, Go to Login Tab then Set Resources. Once again,
Open your Primavera 6.x and check if all Resources were there. You will notice that your
reources category is in Labor already. If OK, then proceed to next step.
Step 13. Set your Manpower Resource Rates. Click on Resource Rates Tab, copy the
Resource ID’s and Description in the sample BOQ provided on the outset of this exercise.
Effective Date and Max Units/Time are just an assumption. You can change as you wish. But
to have the same outcome for this exercise just follow the same. After finishing the tasks,
Go to Login Tab then Set Resource Rates. Once again, Open your Primavera 6.x and check if
all Resource Rates were there. If OK, then proceed to next step.
Step 14. In setting up your Manpower Resource Assignments, Open your Activity 6.x Excel
File. Put your USER NAME and PASSWORD then Update Project List. Select C2 Project. Click
Resource Assignment Tab to setup your Activities. Proceed to the next Step.
Step 15. Set your Manpower Resource Assignment by clicking the Resource Assignment Tab.
Budgeted Units and Remaining Budgeted Units is just the same for a baseline schedule. See
Budgeted Units on our sample BOQ aforementioned in the beginning of this paper. After
finishing the tasks, Go to Login Tab then Set Resource Assignments. Once again, Open your
Primavera 6.x and check if all Resources were correctly assigned. If OK, then proceed to next
step.
That’s it for Schedule Preparation! Now you have the idea how this macro works for
Primavera 6.x then you can try this as well for updating purposes. I hope that you enjoyed it.
CHEERS!!!
- 0AAAhmed Aziz ·
Hi Jeff,Could you please send
Hi Jeff,
Could you please send me a copy of your STEP-BY-STEP GUIDE USING SDK IN SCHEDULE PREPARATION at eng.am.aziz@gmail.com
Thanks,
Ahmed Aziz
- 0MKMemo Kamel ·
Could you please, send me a
Could you please, send me a copy from that SDK.
my email : mka_yusuf@yahoo.com
- 0MKMemo Kamel ·
Could you please, send me a
Could you please, send me a copy from that SDK.
my email : mka_yusuf@yahoo.com