Data label in resources graph

Fayas AhamedMember for 16 years 10 months
Created
2
2
0
Hi to all,
I want add data label (as like in excel) for resources graph.Can i do it in P6,if so how can i add.Please help me

2 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Fayas,
    Unfortunately that is not available in P6. You can add legend but not label for each time period. You can create a stacked histogram with legend if you wish.
  2. 0
    Rashid Iqbal ·
    I will suggest avoid making these graphs in P6..get the data in Excel and deal with it the way you feel like.