Schedule %

Vellu ShanmugamMember for 16 years 10 months
Created
5
2
0
I am not able to roll-out the summary for schedule % although I have indicate the baseline schedule.

Summary (grandtotal) for Duration % and Actual Unit % are ok but schedule % still indicating %.

Please advise.

Regards
Vellu

5 replies

Oldest first
  1. 0
    Shazia khan ·

    if you are ahead of baseline schedule then it may not roll out,

    example baseline activity start date is 25-Sep-10

    but you have start this activity on 25-Aug-10 means you will not able to see your sch.% progress, that will shows after 25-sep-10.

    i am not sure about your problem may be this is the case,
  2. 0
    Vellu Shanmugam ·
    yes i agree with you but my case is the schedule is not ahead. although at each individual activities the schedule % & actual % are indicating figures but when i group it & checked the grandtotal only the actual % showing 6% but schedule % still shows 0%.

    Is there any setting to do with it?

    example;

    activity name; schedule %; actual %;


    Procurement; 100%; 100%
    Manufacture; 52%; 5%;
    Delivery 0%; 0%

    Grandtotal 0%; 6%


  3. 0
    Rashid Iqbal ·
    Vellu,

    Unit and Duration percent will roll up automatically, schedule and physical wont. I will not suggest Duration % but go for Unit % if you can…. and if my memory serves me right there is some way around of rolling up the physical % as well.

    Use only one to display...
  4. 0
    Rodel Marasigan ·
    Vellu,
    If the baseline is not cost loaded then summary will show as zero.
  5. 0
    Vellu Shanmugam ·
    Thank you everyone for your quick support.