Resources Leveling

Rola SabbahMember for 16 years 10 months
Created
2
2
0
Hi everybody,
When i use level resources then schedule F9, all the results of leveling is gone, can any body explain how can i save it? and a little explanation about level resource dialog box it has a lot of options and i’m not sure about.
Thanks

2 replies

Oldest first
  1. 0
    Mike Testro ·
    Hi Rola

    There have been many debates in PP about resource levelling - it may help if you run a search on the subject.

    I do not have P6 but Rodel or some other expert will answer your technical query.

    My stance is that you should never allow the software to level the resources because you have no control over the outcome.

    Best regards

    Mike Testro
  2. 0
    Rodel Marasigan ·
    Rola,
    P6 has an option on Level Resources to Automatically level Resources when Scheduling. Just tick this option and your leveling parameters will be run when running (F9) Schedule.

    Other options are clearly explained on the help button.

Log in or join to reply