Printing Spreadsheet with S-Curve

Ijaz AhmadMember for 20 years 3 months
Created
4
2
0
Hello Guys,
I am trying to print the Spreadsheet at top and S-Curve at bottom of screen in the activities view of P6. But to my surprise there is no Printview and print option available. Can any boy or girl guide me how to make this possible?
Thanks
Ijaz

4 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Ijas,
    Unfortunately that is not possible. P6 has only an option to Print either Spreadsheet or Profile (S-curve) or a combination of Gantt Chart/Profile and Gantt Chart/ Spreadsheet.

    Note: Top View should be at Activity or Gantt Chart View in order to print Spreadsheet or Profile.
  2. 0
    Andrew Dick ·
    Ijaz,
    Using P7 in the tracking view with the ’Resource Allocation by Project’ layout, and doing some grouping and sorting allows this to happen.
    Can’t recal ever doing this in P6 or less. Not sure if this is new or old functionality.

    Give it a crack and see what you come up with.

    I’d post a screen shot but can’t remember how. (such is life)

    Andy
  3. 0
    Ijaz Ahmad ·
    Hi Andrew,
    I tried your solution, but it didn’t work for P6. Even in the tracking layout, it only gives me the print preview for the top view of window and in the options tab of page setup all other options are greyed out. Is there any other solution that can work or we will have to contact the Primavera guys.
    Ijaz
  4. 0
    Andrew Dick ·
    Well I’d be creating a report to take the data out as a HTML file and set it up in excel as a web query data import. Build the s-curve or applicable graphics underneath a table built on the data.
    Maybe even use the data table that can be generated using excel charts.

    I guess that teaches me for thinking there was a way to do it when Rodel said there wasn’t. _ you think I’d learn by now.. LOL

    Andy
    (Now getting back in his box and being quite again)