Schedule % Complete

John SmithsMember for 16 years 3 months
Created
1
1
0
Currently i am using Activity Percent type (Units)

And i update the schedule, but when i compare the Schedule % complete, the schedule % complete is based on duration % of the baseline.

I want to compare it with Actual (Based on units) vs Planned based on units.

How can i do this comparison, I used global change to get the result as i wanted but it doesnt add up in the summary.

Please help?

1 reply

Oldest first
  1. 0
    John Smiths ·
    Thanks a lot was great help.