How to Change Cutt off dates (weekly base)

paulvllnvMember for 16 years 1 month
Created
3
2
0

dear all,

hoa to change the cut off date in P6? in the schedule the cut off date falls every sunday, but i want it to be change every friday. thanks

3 replies

Oldest first
  1. 0
    Niles Luo ·

    How to Change Cutt off dates (weekly base)

    hi,

        We can set it at Admin preferences->General->starting day of week.

    Best Regards.

  2. 0
    Mohamed Azarudeen ·

    Select Enterprise-> Calendar

    Select Enterprise-> Calendar from Primavera menu. Then select which one you need (Global, Resource or Project) to create. Click Add or modify existing and define it from there.

  3. 0
    Zoltan Palffy ·

    admin admin

    admin 

    admin preferences

    General tab

    Starting Dau of Week Chanhe this to Saturday

    this will end the week on Friday