Stange calendar behaviour in P6 V7
- Created
- 3
- 2
Hello Planners,
I am currently working in Algeria, where the workweek starts on Sunday and finishes on Thursday. I have noticed something strange on short 1 day tasks: when the tasks starts on Sunday, the day finishes at 4:00 PM instead of 5:00 PM as on the next task starting on Monday.
Digging into the calendar workweek, I have noticed that the standard work hours are 8:00 AM - 4:00 PM on SUnday with no lunch break, and 8:00AM - 5:00 PM on all other working days with a 1 hour lunch break; when I try to create a 1 hour lunch break, the day is an Exception.
I don't remember having seen such a thing in PM 5 or 6.0
Any idea?
Alexandre, Algeria & France