Price/Unit for resources in Primavera P6
In the Open Standard
Mark DunnMember for 16 years 1 month
- Created
- 5
- 3
0
I have one plan and two P6 users accessing it. The price/unit for resources changes when either of us are in it. There must be a check box somewhere to stop this happening, probably in user preferaces. When one of us use it the price per unit is £39, when the other uses it it is £26.72. Can anyone help?
5 replies