Copy <> function in P3 - anything similar in P6?
In the Open Standard
Eliza CoteMember for 20 years 8 months
- Created
- 0
- 2
0
I often used the <> function in P3 to copy & paste recurring activities. It would allow me to add the floor level, or the facade, or the building wing to the group of activities being copied. I cannot find a similar function in P6 (I am new to P6). Help?