Skip to content

how primavera calculate summary duration -wbs ?

Alaa Al hajMember for 18 years 11 months
Created
7
3
0

 

 

Good morning, 

 

 

i have problem when primavera 6.7 calculate the duration at summary level -wbs

as i have to change admin preference - time period

and this affect other projects

how can we let  primavera calculate duration at WBS level  for each project according to project's calendar

as example now - wbs first activity start on 2-Nov

last activity finish 2-dec

so duration should be 30 days

but it shows only 10 days

i don’t know how  

7 replies

Oldest first
  1. 0
    Michael Ramos ·

    check your assigned global

    check your assigned global calendar

    p6 summary duration are based on global calendar (not project)

  2. 0
    Michael Ramos ·

    check your assigned global

    check your assigned global calendar

    p6 summary duration are based on global calendar (not project)

  3. 0
    Alaa Al haj ·

    Thanks Michael    is there

    Thanks Michael 

     

    is there alternative way to avoid using default calendar

  4. 0
    Michael Ramos ·

    make default global equals

    make default global equals project calendar 

    in p6v7 project calendar can be tick as basis of summary

  5. 0
    Shazia khan ·

    in P6 version 7 ,,,,  you

    in P6 version 7 ,,,,  you have to have tick a global default calender,

    may next version have this option which you  wants,

  6. 0
    Niles Luo ·

    hi, all     When P6v7

    hi, all

        When P6v7 calculate the duration of a WBS element, if all the activities under this WBS element are useing the same calendar, P6v7 will use this calendar. if not, p6v7 will use the default calenar.

    Best Regards

  7. 0
    Khuong Do ·

    Hi,I write an article

    Hi,

    I write an article regarding How does Primavera P6 summarize data in the Summary / Grouping Band. If you're interested kindly read here https://doduykhuong.com/2017/07/10/how-does-primavera-p6-summarize-data-in-the-summary-grouping-band/

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?