Default Calendar in the Schedule
In the Open Standard
Abbas IndiaMember for 17 years 3 months
- Created
- 8
- 2
0
Hi all,
I am developing one Schedule.
In it there are 3 Calendars. E- 8 hrs and 5 days, P- 8hrs and 7 day, C - 8hrs and 6 days.
Please let me know which Calendar I have to keep as default Calendar for the Project? (Enterprise- Projects- Defaults – Calendar)
Thanks,
Abbas
8 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?