P6 : show UPT in column ?
In the Open Standard
Johnny PainMember for 21 years
- Created
- 0
- 4
0
hi all,
I'd like to, as I used to do in P3, show a column in my activity view containing the units/period (or UPT).
it seems I can do it in the resource assignement view, but not in the activity.
I guess it makes sense as multiple resources on one task can be tough to show in one column, but I only have one resource on each task, so it would be really useful.
anyone has ever done it ?
thanks,
djo
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?