Budgeted Units issue from P3 TO P6
In the Open Standard
Minhas ShaikhMember for 19 years 6 months
- Created
- 3
- 1
0
Hi Planners,
I have trasfered data from SAP to P3 then p3 to p6. I got everything except following:
The budgeted hours and original durations are not same. In p3 valueas are same as SAP but not in P6. I think both values are 8 times more. It may cause of some setting or its the way. Can you please resolve my issue as soon as you can. Otherwise I will have to re assign manualy. There are more then 7000 activities.
Thanks
Minhas