Importing including relationship from Excel to P6.

Abbas IndiaMember for 17 years 3 months
Created
4
1
0

Hi all,

Anybody can help me to import activities with relationship from excel to P6.

Is it possible?

Kindly update me.

 

Regards,

Abbas

4 replies

Oldest first
  1. 0
    Jeoffrey Reyes ·

    hi abbas, possible....you can

    hi abbas,

     

    possible....you can use SDK for that...

    cheers,

  2. 0
    Abbas India ·

    Hi Jeff, So are you saying

     

    Hi Jeff,

    So are you saying using normal excel file we cannot import activity relationship information from Microsoft Excel

    Can you guide me how to get SDK and how to use it?

    Kindly update me.

    Regards,

    Abbas

  3. 0
    Stuart Corbett ·

    It is very easy. the quickest

    It is very easy. the quickest way is to do a blank export from Primavera and just use that as a template

  4. 0
    Jeoffrey Reyes ·

    SDK is also using an excel

    SDK is also using an excel file but with macro on it. you can try what stuart is suggesting for a simple excel import-export.

     

    cheers,