Using Different price/Units
In the Open Standard
Aqil MahmoodMember for 21 years 1 month
- Created
- 0
- 2
0
Hi planners
i have assigned two unit rates to my resources i.e Price / unit and Price / Unit 2.
When i am switching over from Price / Unit to Price / Unit 2;
1. The budgeted total cost of program is also changing. This is OK, as desired and understood.
2. But Planned Value cost and Earned value cost is unchanged .This is out of logic to me. Why module is using Price / Unit to calculate these items and why not Price / Unit 2 ?
Please advise accordingly, may be i am missing something.
Would appreciate your quick response
Thankx in advance