WBS - Printing schedule without printing summarized bars of WBS

James MacCammondMember for 15 years 10 months
Created
1
2
0

I would like to know if there is a way to print the schedule without the rolled up (summarized) WBS bars showing.

1 reply

Oldest first
  1. 0
    Ferdinand U. ·

    under bars, you uncheck

    under bars, you uncheck summary bars

Log in or join to reply