Storing Multiple Past Period Performance
- Created
- 3
- 1
Hi PP, hopefully someone can help or answer my question.
I have created a batch of Financial Periods for each week of 2011 (wk1 = 02/01/11 to 09/01/11 etc). But my company has multiple projects which are updated on differenet dates & have different duration intervals between updates. eg some projects are updated weekly on monday, whereas others are updated every 3 weeks.
Is it possible within P6 to store multiple past peroid performance figures over the same dates? So far I have only been able to store past peroid performance weekly. This causes an error for any project that has not been updated within that week.
If I de-select the non-updated projects from a financial period & store the data. When I next update & store the past peroid performance for originally de-selected projects, the past peroid performance data is only stored for one week rather than from the last stored past peroid performance date of that project.
What I require is the ability to store individual projects past peroid performance date over numerous date ranges. These date ranges will overlap. Can this be done? or is there another work around?
Kind regards
Steve Gogarty
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?