P6 Updating schedule problem
In the Open Standard
Abeer MahmoudMember for 18 years 3 months
- Created
- 3
- 2
0
Kindly note that I have a project with more than 100 activities with fixed duration & units and different relations with the following dates as example:
- Activity #1 planned start= 05-dec-10 and planned Finish = 30-dec-10
- Activity #2 planned start= 23-dec-10 and planned Finish = 16-jan-11
And after I updated Activities #1 & 2 by choosing new data date 12-jan-11, selected activity only and based on activity duration type or always recalculate I found the following:
- Activity #1 Actual start= 05-dec-10A & actual Finish = 30-dec-10A
- Activity #2 Actual start= 23-dec-10A & planned Finish = 05-Feb-11 instead of 16-jan-11
I wonder why please clarify the correct steps to update schedule
Best Regards,
Abeer
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?