Skip to content

Actual % complete is showing wrong

Kumar SMember for 16 years 8 months
Created
5
2
0

Dear All

I am updating the progress for my present project.
the project updation is done for every one month.this is the first month of updation.
the acitivites are task dependant.
duration type- fixed duration and units/time.
% complete type- duration type. resources are assighned with cost also
and i have assigned estimation weights to the WBS LEVEL through top down estimation.

after that when i am recording the progrss for the first month the schedule % complete is 2.5%.
after applying the actual to the activities the actual % complete(whch i have selected as duration % complete) is showing as 6.0%. which is not correct because only those activities which were scheduled are completed.
so by logic both the values should be same.

but the actual % complete is showing more

need your guidance please

thanks in advance

5 replies

Oldest first
  1. 0
    Arend Kok ·

    Kumar, You will find that

    Kumar,

    You will find that actual % complete is a function of cost. So you activities are weighted according to their total budgeted cost, and this is used to calculate the % complete on a wbs level.

  2. 0
    Arend Kok ·

    Kumar, You will find that

    Kumar,

    You will find that actual % complete is a function of cost. So you activities are weighted according to their total budgeted cost, and this is used to calculate the % complete on a wbs level.

  3. 0
    Amit Parmar (PMP) ·

    Hi Kumar,The calculation for

    Hi Kumar,

    The calculation for Duration % Complete at summary level is 

    Summary Duration % Complete = ((Summary OD - Summary RD) / Summary OD ) * 100

    here there might be a case where in one of the activities you might have changed the remaining duration and hence the value in the formula changed.

    Try checking the values for the above formula and see if the values satisfy the above equation.

    Arend - Dear Arend, Actual % complete values do not get rolled up to the WBS level whereas Performance % Complete values are rolled up to the WBS and hence they are a function of cost.

     

    Regards

    Amit Parmar

    http://www.primaverablog.in

  4. 0
    Kumar S ·

    Dear Amit, thanks for your

    Dear Amit,

    thanks for your explanation....reminded me of the basics..

    now i checked the all the activities and the remaining duration have not changed for any activity.

    the schedule % complete and the duration % complete should be same,but it is not.

    what i doubt is  i have given weightages to the actvities and the schedule % is calculated depending on the these weightages also.

    but when i am seeing the duaration % complete it is not taking in to consideration these weightges and just showing the percentages depending on the duration % that has been completed till now.

    on the other hand the performance % complete is showing correeclty.

    so can i use this performance % complete for the actual % complete comparision..

     

    thanks in advance

     

  5. 0
    Amit Parmar (PMP) ·

    Hi Kumar,Schedule % COmplete

    Hi Kumar,

    Schedule % COmplete at WBS band is calculated via formula : (BCWS or PV* 100) / BAC

    where

    BCWS or PV = Budgeted Cost of Work Scheduled

    BAC = Budget at Completion

    BCWS or PV = is the portion of the budgeted total cost of the activity that is scheduled to be completed as of the project data dat according to the baseline dates

    BAC = Budgeted total cost in the Baseline

     

    since Schedule % Complete is dependent on cost, the percent complete values might be coming different.

    I would suggest that you compare Performance % complete values and Schedule % Complete values.

    Currently you are trying to compare 2 values which are calcluated by different parameters.

    Regards

    Amit Parmar

    http://www.primaverablog.in

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?