Skip to content

baseline activities does not appear in the present schedule

Kumar SMember for 16 years 8 months
Created
3
2
0

 

Dear All
 
I am now working on a project.
the project has started on jan 2011.
so one month is over and i am updating the project for each  month.
now i had to add some activites to the baseline project so i used the restore baseline option.there i added the actitiies and deleted 2 activities schduled it and again assigned it to the present project
but now in the present project those actitivtes are not appearing.
i checked in the maintain baseline option, the updated baseline is assigned correctly.
 
what should i do to get the added activities in the present project
 
thanks in advance

3 replies

Oldest first
  1. 0
    Raymund de Laza ·

    Hi Mr. Kumar, You can not

    Hi Mr. Kumar,

    You can not find the Added Activities because it was in the Baseline Project. What you will see in the Current open Project is only the activities of the current open project.

    You should add the Activity ID of those activities you added as well as their Activty names into the current open project.

    Baselining a project means that you want to compare current open project schedule to a TARGET project schedule (Baseline Project).

    Activity DATA of baseline activities will appear only if baseline Activity ID is matching with Activity ID's of current open project.

    Hope this will satisfy your requirements.

     

    Regards,

  2. 0
    Kumar S ·

    dear raymond thank you very

     dear raymond

    thank you very much.

    i will now add the those activities which i have aaded in the baseline project  with the same activity ID duaration/relationship /resources and schedule the present project.

    But i have small query

    since i have already put the actual dates in the present project an scheduled it the start date for many activities have changed accordingly.

    so when i link these new activitities with the progressed actitities i ahve to change the timimg by putting lags and make the new activities start in the same time as it has statred in the baseline schedule.

    please let me if my approach is right

     

    thanks in advance

     

     

  3. 0
    Raymund de Laza ·

    Mr. Kumar, You shall add the

    Mr. Kumar,

    You shall add the new activities into the current open project with the same relationships and lags as with that you did in the baseline project then schedule it.

    The updated schedule dates will now be differ from your baseline projects dates if the updated schedule actual dates is not the same as the start/finish dates of the baseline project.

     

    Regards,

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?