strange issue with the baseline schedule
- Created
- 7
- 4
Dear All
i am facing a strange issue for one of my projects.
presently i m working for a project which has started on 1st jan 2011.
now i have assigned the baseline and started updating.
now since there was some changes to be made with the baseline schedule i had restored the baseline project made the necessery changes and again assigned it back to the present project.everyhting is fine till now.
but when i open the same project in one of my colleagues computer the base line date is showing same as the present project date.first i spent a lot of time to find out why was this happening because in my computer it was showing correctly but other computers its not.
then what i saw was in the assign baseline section the baseline schedule attached is "CURRENT PROJECT".this is quite strange because i had already selected the baseline in my computer.
i saw that this happens when evre you re baseline any schedule.
so what may be the reson for this.is there any option where in we can keep the baseline schedule same where ever we login.
thanks in advance
7 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?