WBS

Khairul Izani OthmanMember for 18 years 11 months
Created
5
1
0

Hello all,

I have a problem regarding WBS..

If 1000 activity i can export from excell sheet..how about WBS?

Simple WBS can be create directly from P6 WBS section, but how about to create 1000 list of WBS?..

Example:

1 A  
  1.1 A1
  1.2 A2
  until
  1.1000 A1000
   

Hope to hear something from you all..thank very much..

5 replies

Oldest first
  1. 0
    Kumar Baiju ·

    Hello Khairul      have you

    Hello Khairul

         have you made only activity in excel and you want to export or you export from P6 and after some changing you want to import. plesae give detail

    KBJ

  2. 0
    Kumar Baiju ·

    Hello Khairul      have you

    Hello Khairul

         have you made only activity in excel and you want to export or you export from P6 and after some changing you want to import. plesae give detail

    KBJ

  3. 0
    Khairul Izani Othman ·

    Hi kumar, Actually i want to

    Hi kumar,

    Actually i want to make the WBS first..this time with no activity yet..after complete the WBS, then i will create the activity.

    For me, the activity insert is not a problem. WBS insert is the problem..

    Any suggestion? 

  4. 0
    Raymund de Laza ·

    Hi, Make use of the WBS

    Hi,

    Make use of the WBS import/export utility from excel.

     

    Regards,

  5. 0
    Khairul Izani Othman ·

    Hi Mr. Raymund, That was good

    Hi Mr. Raymund,

    That was good news for me..but still cannot make that import/export for WBS..maybe i miss something..

    Could you give detail how to import WBS into the P6?

     

    Thank and regards,